Call (540)
636-9973 to schedule an inspection. You must call before 4:00 p.m. for
your inspection to be scheduled the next business day.  For further information: (540) 636-9973.
Required Inspections:
Foundation Footings: Inspection required after all trench, pier or other
type of foundation footing forms are dug and or constructed but prior to
placement of concrete.
Concrete Formwork: Inspection required for all vertical and horizontal formwork
before placement of concrete.
Foundation: Inspection required of all foundations below grade prior to
back filling. All foundation drains, gravel cover, filter cloth and
foundation coating and parging shall be completed.
Chimney/Fireplaces/Hearth: Call for throat and/or thimble inspection
before proceeding with chimney and before pouring hearth.
Framing: After all framing, fire stopping and bracing is complete and
prior to insulating.
Plumbing: After all "rough-in" plumbing has been installed and
prior to any concealment by insulation, wall coverings, concrete or other
concealing material.
Mechanical: After ductwork is installed and prior to insulation.
Insulation: After insulation and energy seals have been installed and
before wall covering is installed.
Final Inspection: All work has been completed and the building or structure is
ready for use and/or occupancy. Final approval can not be issued until
compliance with all other applicable state and county codes have been verified.